Content Provider | Supreme Court of India |
---|---|
e-ISSN | 30484839 |
Language | English |
Access Restriction | NDLI |
Subject Keyword | Arbitration and Conciliation Act 1996 |
Content Type | Text |
Resource Type | Law Judgement |
Jurisdiction | India |
Act(s) Referred | Arbitration and Conciliation Act, 1996 (26 of 1996) |
Case(s) Referred | Referred Case 0 Referred Case 1 Referred Case 2 |
Case Type | Appeal |
Court | Supreme Court of India |
Disposal Nature | Appeal Allowed |
Headnote | Arbitration and Conciliation Act, 1996: ss.34 and 37 – Contract awarded for maintenance of road for Rs.5.26 crores – The rate of maintenance of the road was accepted at Rs.1,000 per km p.m. – Maintenance contract was valid up to 31.07.2010 – Contract was meant for only 3364 PCUS per day – Dispute arose when contractor was required to incur additional expenditure on maintenance due to diversion of traffic from Palwal Aligarh Road to the present road and heavy traffic of 24418 PCUS per day started plying on the road which damaged the road – Contractor claimed the amount towards additional expenditure for maintenance – Arbitrator awarded Rs.1.51 crores taking loss at Rs.45,000 per km per month (claim Nos.1 and 8) – Case on behalf of the State-appellant was that in the statement of claim, the claimant claimed an amount of Rs.1.03 crores under claim Nos. 1 and 8 and, therefore award was in excess of amount claimed – Held: No substance in this contention – The statement of claim submitted by contractor specifically stated that amount of Rs.1.03 crores was worked out up to May, 2007 and details of expenditure beyond May,2007 will be submitted during the course of hearing – Therefore,amount awarded by the arbitrator cannot be said to be in excess of the claim – So far as the submission on behalf of the appellant that the arbitrator exceeded the scope of reference while awarding an amount beyond 19.05.2007-the date on which the High Court appointed the sole arbitrator is concerned, same has no substance – Case of appellant that Arbitrator ought to have restricted the claim either up to 06.03.2006-the date on which the contractor invoked the arbitration clause or 23.04.2007, the date on which the High Court appointed the sole arbitrator or at least up to 19.05.2007-the date on which the arbitrator entered into reference cannot be accepted since the award made by the arbitrator was till the traffic was diverted which was up to January, 2008 – Therefore, the arbitrator was justified in awarding the amount beyond the said periods and till the additional traffic was diverted – Third submission on behalf of the appellant was that by awarding Rs.45,000 per km per month, the arbitrator has rewritten the contract with respect to the amount payable than what was specified in the contract – At the time when contract was entered into the mutually agreed, the rate fixed was Rs.1,000 per km per month and the estimated traffic was 3364 PCUS per day – Cause of action arose subsequently due to diversion of traffic from Palwal Aligarh Road and plying of more heavy vehicles due to which the contractor was required to incur additional expenditure for maintenance of the road – Therefore, the contractor was entitled to the loss on account of the additional expenditure incurred for maintenance of the road – By no stretch of imagination, it can be said that there was rewriting the terms of the contract as submitted on behalf of the appellant – However, arbitrator ought not to have awarded an amount of Rs.45,000 per km p.m. beyond the time period of additional traffic – Arbitrator has awarded the loss/amount at Rs.45,000 per km per month up to 31.05.2010 i.e. till the end of the contract which is wholly impermissible diversion of the additional traffic cease dto exist w.e.f. January, 2008 – Therefore, the arbitrator ought not to have awarded any amount beyond the above time period beyond January, 2008 – To that extent the award passed by the arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed. |
Judge | Hon'ble Mr. Justice M.R. Shah |
Neutral Citation | 2021 INSC 888 |
Petitioner | State Of Haryana |
Respondent | M/s. Shiv Shankar Construction Co. & Anr. |
SCR | [2021] 12 S.C.R. 294 |
Judgement Date | 2021-12-14 |
Case Number | 7379 |
National Digital Library of India (NDLI) is a virtual repository of learning resources which is not just a repository with search/browse facilities but provides a host of services for the learner community. It is sponsored and mentored by Ministry of Education, Government of India, through its National Mission on Education through Information and Communication Technology (NMEICT). Filtered and federated searching is employed to facilitate focused searching so that learners can find the right resource with least effort and in minimum time. NDLI provides user group-specific services such as Examination Preparatory for School and College students and job aspirants. Services for Researchers and general learners are also provided. NDLI is designed to hold content of any language and provides interface support for 10 most widely used Indian languages. It is built to provide support for all academic levels including researchers and life-long learners, all disciplines, all popular forms of access devices and differently-abled learners. It is designed to enable people to learn and prepare from best practices from all over the world and to facilitate researchers to perform inter-linked exploration from multiple sources. It is developed, operated and maintained from Indian Institute of Technology Kharagpur.
Learn more about this project from here.
NDLI is a conglomeration of freely available or institutionally contributed or donated or publisher managed contents. Almost all these contents are hosted and accessed from respective sources. The responsibility for authenticity, relevance, completeness, accuracy, reliability and suitability of these contents rests with the respective organization and NDLI has no responsibility or liability for these. Every effort is made to keep the NDLI portal up and running smoothly unless there are some unavoidable technical issues.
Ministry of Education, through its National Mission on Education through Information and Communication Technology (NMEICT), has sponsored and funded the National Digital Library of India (NDLI) project.
Sl. | Authority | Responsibilities | Communication Details |
---|---|---|---|
1 | Ministry of Education (GoI), Department of Higher Education |
Sanctioning Authority | https://www.education.gov.in/ict-initiatives |
2 | Indian Institute of Technology Kharagpur | Host Institute of the Project: The host institute of the project is responsible for providing infrastructure support and hosting the project | https://www.iitkgp.ac.in |
3 | National Digital Library of India Office, Indian Institute of Technology Kharagpur | The administrative and infrastructural headquarters of the project | Dr. B. Sutradhar bsutra@ndl.gov.in |
4 | Project PI / Joint PI | Principal Investigator and Joint Principal Investigators of the project |
Dr. B. Sutradhar bsutra@ndl.gov.in Prof. Saswat Chakrabarti will be added soon |
5 | Website/Portal (Helpdesk) | Queries regarding NDLI and its services | support@ndl.gov.in |
6 | Contents and Copyright Issues | Queries related to content curation and copyright issues | content@ndl.gov.in |
7 | National Digital Library of India Club (NDLI Club) | Queries related to NDLI Club formation, support, user awareness program, seminar/symposium, collaboration, social media, promotion, and outreach | clubsupport@ndl.gov.in |
8 | Digital Preservation Centre (DPC) | Assistance with digitizing and archiving copyright-free printed books | dpc@ndl.gov.in |
9 | IDR Setup or Support | Queries related to establishment and support of Institutional Digital Repository (IDR) and IDR workshops | idr@ndl.gov.in |