Disposal Nature | Appeal Allowed |
Headnote | Electricity Act, 2003 : ss. 2(17), 12, 14, 43, 61, 62 and 64 – Determination of tariff – Exercise of ‘truing up’ – Appellants are distribution licensees, involved in distributing and supplying electricity in their designated areas within the NCT of Delhi – In terms of the 2003 Act, Delhi Electricity Regulatory Commission DERC, regulated the Annual revenue requirement-ARR of the appellants to conduct the licensed business and consequently the tariff to be recovered from the consumers – DERC made disallowances in Tariff orders dated 26.08.2012 for determination of ARR and Tariff for FY 2011-12 and truing up of financials for FY 2008-09 and FY 2009-10 – DERC changed methodology of computation of ARR at the stage of true up – Challenged by the appellants before the appellate tribunal for Electricity – Appellants contented that since privatization, the ARR determined by the DERC was not even sufficient to meet the actual power purchase cost which led to creation of a huge revenue gap; that the DERC in repeated disregard to its statutory regulations and its own statutory advice refused to make periodic increase in the tariff rate, leading to the indebtness of appellants – Findings of DERC confirmed by APTEL – On appeal, held: It is not permissible to amend the tariff order during true up exercise – On the pretext of prudence check and truing up, DERC could not have amended the tariff order – Regulator cannot ‘change the rules after it has begun’ in the ‘truing up exercise’ – Thus, the findings of the DERC, as confirmed by the APTEL in the on issues pertaining to change in methodology in computation of AT&C losses; change in methodology for computation of depreciation; disallowance of salary for FR/SR Structure; and disallowance of Fringe Benefit Tax, are contrary to the order of the original MYT determination Tariff Order dated 23.02.2008 and 28.05.2009, thus, set aside – As regards the disallowance of interest incurred on Consumer Security Deposit retained by DPCL, the appellants are entitled to recover interest on Consumers Security Deposit as held by the DPCL – As regards, reduction in million units in relation to enforcement sale for the purpose of calculation of Aggregate Technical and Commercial losses, pertaining to theft/unauthorized use of electricity, the assessed energy has to be considered as supply by the appellants in the enforcement cases – DERC to consider assessed energy for calculation of enforcement sales and allow the impact of the same along with carrying costs – Thus, the order of the DERC and the judgment of the APTEL impugned herein are set aside.s. 64 – Procedure for tariff order – Amendment of tariff order made u/s. 64 during the ‘truing up’ exercise – Permissibility of – Held: A tariff order is quasi-judicial in nature which becomes final and binding on the parties unless it is amended or revoked u/s. 64(6) or set aside by the appellate authority – ‘Truing up’ stage is not an opportunity for the DERC to rethink de novo on the basic principles, premises and issues involved in the initial projections of the revenue requirement of the licensee – ‘Truing up’ exercise cannot be done to retrospectively change the methodology/principles of tariff determination and re- opening the original tariff determination order thereby setting the tariff determination process to a naught at ‘true-up’ stage – Revision or re-determination of the tariff already determined by DERC on the pretext of prudence check and truing up would amount to amendment of the tariff order, which can be done only as per the provisions of sub-Section (6) of s.64 within the period for which the Tariff Order was applicable – DERC cannot amend the tariff order for the period 01.04.2008 to 31.03.2010 in the guise of ‘true-up’ after the relevant financial year is over and the same is replaced by a subsequent tariff Order – This would amount to a retrospective revision of tariff when the relevant period for such tariff order is already over – Thus, not permissible to amend the tariff order made u/s. 64 during the ‘truing up’ exercise.s. 125 – Appeal to Supreme Court – Exercise of jurisdiction under – Held: Existence of a ‘substantial question of law’ arising from the judgment of the APTEL is sine qua non for exercise of jurisdiction by this Court u/s. 125 – Code of Civil Procedure – s. 100. ‘Truing up’ – Meaning of – Held: ‘Truing up’ is the adjustment of actual amounts incurred by the licensee against the estimated/projected amounts determined under the Annual revenue requirement-ARR.‘Substantial Question of Law’ – Meaning of – Discussed. ‘Appeal’ – Meaning – Discussed. |
Judge | Hon'ble Mr. Justice S. Abdul Nazeer |
Neutral Citation | 2022 INSC 1105 |
Petitioner | Bses Rajdhani Power Ltd. |
Respondent | Delhi Electricity Regulatory Commission |
SCR | [2022] 14 S.C.R. 790 |
Judgement Date | 2022-10-18 |
Case Number | 4324 |
National Digital Library of India (NDLI) is a virtual repository of learning resources which is not just a repository with search/browse facilities but provides a host of services for the learner community. It is sponsored and mentored by Ministry of Education, Government of India, through its National Mission on Education through Information and Communication Technology (NMEICT). Filtered and federated searching is employed to facilitate focused searching so that learners can find the right resource with least effort and in minimum time. NDLI provides user group-specific services such as Examination Preparatory for School and College students and job aspirants. Services for Researchers and general learners are also provided. NDLI is designed to hold content of any language and provides interface support for 10 most widely used Indian languages. It is built to provide support for all academic levels including researchers and life-long learners, all disciplines, all popular forms of access devices and differently-abled learners. It is designed to enable people to learn and prepare from best practices from all over the world and to facilitate researchers to perform inter-linked exploration from multiple sources. It is developed, operated and maintained from Indian Institute of Technology Kharagpur.
Learn more about this project from here.
NDLI is a conglomeration of freely available or institutionally contributed or donated or publisher managed contents. Almost all these contents are hosted and accessed from respective sources. The responsibility for authenticity, relevance, completeness, accuracy, reliability and suitability of these contents rests with the respective organization and NDLI has no responsibility or liability for these. Every effort is made to keep the NDLI portal up and running smoothly unless there are some unavoidable technical issues.
Ministry of Education, through its National Mission on Education through Information and Communication Technology (NMEICT), has sponsored and funded the National Digital Library of India (NDLI) project.
Sl. | Authority | Responsibilities | Communication Details |
---|---|---|---|
1 | Ministry of Education (GoI), Department of Higher Education |
Sanctioning Authority | https://www.education.gov.in/ict-initiatives |
2 | Indian Institute of Technology Kharagpur | Host Institute of the Project: The host institute of the project is responsible for providing infrastructure support and hosting the project | https://www.iitkgp.ac.in |
3 | National Digital Library of India Office, Indian Institute of Technology Kharagpur | The administrative and infrastructural headquarters of the project | Dr. B. Sutradhar bsutra@ndl.gov.in |
4 | Project PI / Joint PI | Principal Investigator and Joint Principal Investigators of the project |
Dr. B. Sutradhar bsutra@ndl.gov.in Prof. Saswat Chakrabarti will be added soon |
5 | Website/Portal (Helpdesk) | Queries regarding NDLI and its services | support@ndl.gov.in |
6 | Contents and Copyright Issues | Queries related to content curation and copyright issues | content@ndl.gov.in |
7 | National Digital Library of India Club (NDLI Club) | Queries related to NDLI Club formation, support, user awareness program, seminar/symposium, collaboration, social media, promotion, and outreach | clubsupport@ndl.gov.in |
8 | Digital Preservation Centre (DPC) | Assistance with digitizing and archiving copyright-free printed books | dpc@ndl.gov.in |
9 | IDR Setup or Support | Queries related to establishment and support of Institutional Digital Repository (IDR) and IDR workshops | idr@ndl.gov.in |