Content Provider | Supreme Court of India |
---|---|
e-ISSN | 30484839 |
Language | English |
Access Restriction | NDLI |
Subject Keyword | Arbitration and Conciliation Act 1996 |
Content Type | Text |
Resource Type | Law Judgement |
Jurisdiction | India |
Case Type | Appeal |
Court | Supreme Court of India |
Disposal Nature | Appeal Dismissed |
Headnote | Issue for consideration:Arbitral award in question if in conflict with the public policy of India and; whether a claim on account of loss of profit is liable to succeed merely on the ground that there has been delay in the execution of the construction contract, attributable to the employer.Arbitration and Conciliation Act, 1996 – s.34(2)(b) – “Public policy of India” – Appellant awarded work contract by the respondent – Disputes between the parties owing to the delay in work, referred to Arbitrator – Vide First Award, appellant was awarded sum towards loss of profit (Claim No.12) – Award set aside by High Court, claims remitted to the Arbitrator – Second Award was passed maintaining the award for loss of profit and interest to the appellant vide First Award – Respondent filed petition u/s.34 for setting aside the second Award – Single Judge allowed the objection, rejected the appellant's claim inter alia holding that there was no sufficient evidence presented by the appellant to establish the claimed loss of profit – Order affirmed by Division Bench:Held: Second Award is equally in conflict with the public policy of India as the First Award – While remitting Claim No.12 for reconsideration, the Arbitrator was warned not to be influenced by the factors that weighed in his mind while making the First Award – Arbitrator was also required to proceed only on the basis of the evidence – However, the Arbitrator went on to ignore the judicial decision of the High Court with impunity – The factors which weighed in the Arbitrator’s mind in the first round and the second round are one and the same – To avoid any charge of being branded as a mirror image of the First Award insofar as Claim No.12 is concerned, the Second Award appears to have been expressed in language and form different from the earlier one without, however, there being any change in substance – A judicial decision of a superior court, which is binding on an inferior court, has to be accepted with grace by the inferior court notwithstanding that the decision of the superior court may not be palatable to the inferior court – This principle, ex proprio vigore, would be applicable to an arbitrator and a multi-member arbitral tribunal as well, particularly when it is faced with a judicial decision (either u/s.34 or s.37 of the Act) ordering a limited remand – In the wake of authority of judicial determination made by the Courts of law, any award of an arbitrator or a tribunal that seeks to overreach a binding judicial decision does conflict with the fundamental public policy and thus, cannot be sustained – Further, a claim for damages, whether general or special, cannot as a matter of course result in an award without proof of the claimant having suffered injury – Arbitral award in question is patently illegal in that it is based on no evidence and is, thus, outrightly perverse; therefore, again, it is in conflict with the “public policy of India” as contemplated by s.34(2)(b) – No merit in the appeal. [Paras 13, 14 and 20]Arbitration – Claim for loss of profit arising from a delayed contract or missed opportunities from other available contracts – Claimant to substantiate the presence of a viable opportunity through compelling evidence demonstrating that had the contract been executed promptly, the contractor could have secured supplementary profits utilizing its existing resources elsewhere – Nature and quality of such evidence:Held: Will be contingent upon the facts and circumstances of each case – However, it may generally include independent contemporaneous evidence such as other potential projects that the contractor had in the pipeline that could have been undertaken if not for the delays, the total number of tendering opportunities that the contractor received and declined owing to the prolongation of the contract, financial statements, or any clauses in the contract related to delays, extensions of time, and compensation for loss of profit – This list is not exhaustive and may include any other piece of evidence that the court may find relevant – In adjudging a claim towards loss of profits, the court may not make a guess in the dark; the credibility of the evidence, therefore, is the evidence of the credibility of such claim – Thus, for claims related to loss of profit, profitability or opportunities to succeed, one would be required to establish that there was a delay in the completion of the contract; that such delay is not attributable to the claimant; that the claimant’s status as an established contractor, handling substantial projects; and credible evidence to substantiate the claim of loss of profitability – In the present case, the fourth condition, namely, the evidence to substantiate the claim of loss of profitability remains unfulfilled. [Paras 17, 19]Arbitration – Contractor's claims for loss of profit – Hudson’s formula:Held: Hudson’s formula though has attained acceptability and is well understood in trade, however, it does not apply in a vacuum – Hudson’s formula, as well as other methods used to calculate claims for loss of off-site overheads and profit, do not directly measure the contractor's exact costs – Instead, they provide an estimate of the losses the contractor may have suffered – While these formulae are helpful when needed, they alone cannot prove the contractor's loss of profit – They are useful in assessing losses, but only if the contractor has shown with evidence the loss of profits and opportunities it suffered owing to the prolongation. [Para 18] |
Judge | Hon'ble Mr. Justice Dipankar Datta |
Neutral Citation | 2023 INSC 931 |
Petitioner | M/s Unibros |
Respondent | All India Radio |
SCR | [2023] 14 S.C.R. 683 |
Judgement Date | 2023-10-19 |
Case Number | 6895 |
National Digital Library of India (NDLI) is a virtual repository of learning resources which is not just a repository with search/browse facilities but provides a host of services for the learner community. It is sponsored and mentored by Ministry of Education, Government of India, through its National Mission on Education through Information and Communication Technology (NMEICT). Filtered and federated searching is employed to facilitate focused searching so that learners can find the right resource with least effort and in minimum time. NDLI provides user group-specific services such as Examination Preparatory for School and College students and job aspirants. Services for Researchers and general learners are also provided. NDLI is designed to hold content of any language and provides interface support for 10 most widely used Indian languages. It is built to provide support for all academic levels including researchers and life-long learners, all disciplines, all popular forms of access devices and differently-abled learners. It is designed to enable people to learn and prepare from best practices from all over the world and to facilitate researchers to perform inter-linked exploration from multiple sources. It is developed, operated and maintained from Indian Institute of Technology Kharagpur.
Learn more about this project from here.
NDLI is a conglomeration of freely available or institutionally contributed or donated or publisher managed contents. Almost all these contents are hosted and accessed from respective sources. The responsibility for authenticity, relevance, completeness, accuracy, reliability and suitability of these contents rests with the respective organization and NDLI has no responsibility or liability for these. Every effort is made to keep the NDLI portal up and running smoothly unless there are some unavoidable technical issues.
Ministry of Education, through its National Mission on Education through Information and Communication Technology (NMEICT), has sponsored and funded the National Digital Library of India (NDLI) project.
Sl. | Authority | Responsibilities | Communication Details |
---|---|---|---|
1 | Ministry of Education (GoI), Department of Higher Education |
Sanctioning Authority | https://www.education.gov.in/ict-initiatives |
2 | Indian Institute of Technology Kharagpur | Host Institute of the Project: The host institute of the project is responsible for providing infrastructure support and hosting the project | https://www.iitkgp.ac.in |
3 | National Digital Library of India Office, Indian Institute of Technology Kharagpur | The administrative and infrastructural headquarters of the project | Dr. B. Sutradhar bsutra@ndl.gov.in |
4 | Project PI / Joint PI | Principal Investigator and Joint Principal Investigators of the project |
Dr. B. Sutradhar bsutra@ndl.gov.in Prof. Saswat Chakrabarti will be added soon |
5 | Website/Portal (Helpdesk) | Queries regarding NDLI and its services | support@ndl.gov.in |
6 | Contents and Copyright Issues | Queries related to content curation and copyright issues | content@ndl.gov.in |
7 | National Digital Library of India Club (NDLI Club) | Queries related to NDLI Club formation, support, user awareness program, seminar/symposium, collaboration, social media, promotion, and outreach | clubsupport@ndl.gov.in |
8 | Digital Preservation Centre (DPC) | Assistance with digitizing and archiving copyright-free printed books | dpc@ndl.gov.in |
9 | IDR Setup or Support | Queries related to establishment and support of Institutional Digital Repository (IDR) and IDR workshops | idr@ndl.gov.in |