Content Provider | Supreme Court of India |
---|---|
e-ISSN | 30484839 |
Language | English |
Access Restriction | NDLI |
Subject Keyword | 2003: ss. 61 to 63 - Commercial Operation Date (COD) - Determination of- Procurement of power from generating companies - Sasan Power Ltd. was incorporated as a special purpose vehicle by Power Finance corporation the nodal agency for procuring power - Power Purchase Agreement (PPA) ELECTRICITY ACT |
Content Type | Text |
Resource Type | Law Judgement |
Jurisdiction | India |
Case Type | Appeal |
Court | Supreme Court of India |
Disposal Nature | Appeal Allowed |
Headnote | ELECTRICITY ACT, 2003: ss. 61 to 63 - Commercial Operation Date (COD) - Determination of- Procurement of power from generating companies - Sasan Power Ltd. was incorporated as a special purpose vehicle by Power Finance corporation the nodal agency for procuring power - Power Purchase Agreement (PPA) dated 7.8.2007 executed between Sasan Power Ltd. and procurers of generation and sale of electricity - Article 6 r/w Schedule 5 provided for preconditions to be satisfied for declaration of 'COD' namely readiness to commence commercial operations - This happens only when the pe1formance test by operating the gene1·ating unit at 98% of the contracted capacity as existing on the effective date on a continuous running basis for 72 hours is certified by an independent engineer by giving a final test certificate to the said effect - The date for commissioning the first unit was fixed under the PPA as 7.5.2013 - However, under Schedule 11 thereof. this date was preponed to 27.11.2012 - As Sasan kept postponing this date, the commissioning tests for generating Unit No.3 commenced from 20.3.2013 - Various emails were exchanged from 27.3.2013 to 30.3.2013 between Sasan and WRLDC, a statutory authority under the Act of 2003 - It was the case of Sasan that though they were ready to deliver electricity on 31.3.2013 at 95% of the contracted capacity of 620 MW of the unit, they could not do so as WRLDC did not give them the necessary green signal to go ahead - They relied heavily upon the independent engineer's test certificate dated 30.3.2013 to show that a COD took place on the following day - Petition was filed by WRLDC before the CER Commission challenging the veracity of certificate issued by the independent engineer - Commission arrived at the conclusion that COD had not been achieved on 31.3.2013 but had only beenachieved tater on 16.8.2013 - Appellate Tribunal set aside the finding of Commission holding that though COD had not been achieved on 31.3.2013 in accordance with the PPA but that the procurers under the PPA had waived their right to demand performance at 95% and that the pe1formance of unit no.3 which was only roughly 17% of its contracted capacity was accepted by all the procurers and that, therefore, there was a waiver of this essential condition which would then entitle the generator to treat 31.3.2013 as the-date on which commercial operation of unit no.3 commenced - Challenged - Held: A perusal of the emails exchanged between the parties show that the parties did not intend to amend any of the provisions of the PPA - The two emails sent by the lead procurer to Sasan read together do not amount to waiver of the right mentioned in clause 6.3.1 - There is no .such clear intention that can be spelled out on a reading of the two emails - All that can be spelled out is that the first email of 31.3.2013 categorically stated that the test result is not as per Article 6.3.1, and is not acceptable - The last sentence of this very email then refers to clause 6.3.4 and to a de-rated capacity of 101.38 MW - Thereafter, email of 2..1.2013 expands on the said last sentence of the earlier email by referring to Article 6.3.4 and Article 11 proviso - This is akin to a 'without prejudice' acceptance of de-rated power, being a non-acceptance of the test certificate dated 30.3.2013 coupled with a desperate attempt to somef10w get whatever power is available - But this does not amount to a clear and unequivocal intention to relinquish a known right - There is no waiver - Appellate Tribunal is wholly incorrect in accepting the case of waiver and is equally incorrect in absolving the, independent engineer for the test cer.tificate given by him on 30.3.2013.ss. 61 to 63 - Electricity tariff- Variation in - Effect on public interest - Held: The moment electricity tariff gets affected, the consumer interest comes in and public interest gets affected - Under s.61, the appropriate commission, when ·it specifies terms and G conditions for determination of tariff, is to be guided inter alia by the safeguarding of the consumer interest and the recovery of the cost of electricity in a reasonable manner.WAIVER: H Waiver of right - Held: Waiver is an intentional relinquishmentof a known right - Waiver must be ~pelled out with crystal clarity for there must be a clear intention to give up a known right - Therefore, unless there is a clear intention to relinquish a right that is fully known to a party, a party cannot be said to waive it. Waiver of provision of contract if any element of public interest is involved - Held: Such waiver will not be given effect to if it is contrary to such public interest - If there is any element of public interest involved, the court steps in to thwart any waiver which may be contrary to such public interest - Judicial review - Electricity Act, 2003. Contract Act, 1872: s.63 -Applicability of- Held: If on facts there is a waiver of a provision of the PPA by one of the parties to the PPA, then s.63 of the Contract Act will operate in order to give effect to such waiver - Waiver. |
Judge | Hon'ble Mr. Justice R.F. Nariman |
Neutral Citation | 2016 INSC 1114 |
Petitioner | All India Power Engineer Federation & Ors. |
Respondent | Sasan Power Ltd. & Ors. Etc. |
SCR | [2016] 9 S.C.R. 901 |
Judgement Date | 2016-12-08 |
Case Number | 5881-5882 |
National Digital Library of India (NDLI) is a virtual repository of learning resources which is not just a repository with search/browse facilities but provides a host of services for the learner community. It is sponsored and mentored by Ministry of Education, Government of India, through its National Mission on Education through Information and Communication Technology (NMEICT). Filtered and federated searching is employed to facilitate focused searching so that learners can find the right resource with least effort and in minimum time. NDLI provides user group-specific services such as Examination Preparatory for School and College students and job aspirants. Services for Researchers and general learners are also provided. NDLI is designed to hold content of any language and provides interface support for 10 most widely used Indian languages. It is built to provide support for all academic levels including researchers and life-long learners, all disciplines, all popular forms of access devices and differently-abled learners. It is designed to enable people to learn and prepare from best practices from all over the world and to facilitate researchers to perform inter-linked exploration from multiple sources. It is developed, operated and maintained from Indian Institute of Technology Kharagpur.
Learn more about this project from here.
NDLI is a conglomeration of freely available or institutionally contributed or donated or publisher managed contents. Almost all these contents are hosted and accessed from respective sources. The responsibility for authenticity, relevance, completeness, accuracy, reliability and suitability of these contents rests with the respective organization and NDLI has no responsibility or liability for these. Every effort is made to keep the NDLI portal up and running smoothly unless there are some unavoidable technical issues.
Ministry of Education, through its National Mission on Education through Information and Communication Technology (NMEICT), has sponsored and funded the National Digital Library of India (NDLI) project.
Sl. | Authority | Responsibilities | Communication Details |
---|---|---|---|
1 | Ministry of Education (GoI), Department of Higher Education |
Sanctioning Authority | https://www.education.gov.in/ict-initiatives |
2 | Indian Institute of Technology Kharagpur | Host Institute of the Project: The host institute of the project is responsible for providing infrastructure support and hosting the project | https://www.iitkgp.ac.in |
3 | National Digital Library of India Office, Indian Institute of Technology Kharagpur | The administrative and infrastructural headquarters of the project | Dr. B. Sutradhar bsutra@ndl.gov.in |
4 | Project PI / Joint PI | Principal Investigator and Joint Principal Investigators of the project |
Dr. B. Sutradhar bsutra@ndl.gov.in Prof. Saswat Chakrabarti will be added soon |
5 | Website/Portal (Helpdesk) | Queries regarding NDLI and its services | support@ndl.gov.in |
6 | Contents and Copyright Issues | Queries related to content curation and copyright issues | content@ndl.gov.in |
7 | National Digital Library of India Club (NDLI Club) | Queries related to NDLI Club formation, support, user awareness program, seminar/symposium, collaboration, social media, promotion, and outreach | clubsupport@ndl.gov.in |
8 | Digital Preservation Centre (DPC) | Assistance with digitizing and archiving copyright-free printed books | dpc@ndl.gov.in |
9 | IDR Setup or Support | Queries related to establishment and support of Institutional Digital Repository (IDR) and IDR workshops | idr@ndl.gov.in |